Role of the Project Scheduler (PMI-SP)

What is the role of a scheduler? Scheduler performs many tasks. The tasks he will do will be assigned to him by a project manager. His tasks could include:

  • Gathering schedule data (milestones, activities and their attributes e.g. dates, except risk activities)

  • Attending meetings to discuss schedule, format, reporting format.

  • Revising schedule.

  • Update plan with actual progress of activities, resources productivity rates.

  • Analysis of plan and actual progress.

  • Analyzing critical path

  • Perform resource leveling

  • Creating reports of plan, actual and forecasted schedule.

  • Creating Work Breakdown Structure (WBS)

  • Creating Organizational Breakdown Structure (OBS)

  • Creating Resource Breakdown Structure (RBS)

Activity Duration Estimation Techniques (PMI-SP)

Analogous estimation technique:

It is a comparison technique where we look at a similar activity performed before. If more data is available, the better the estimate will be.

Parametric estimation technique:

Parameters from previous similar activity is taken. E.g. Previous activity took 5 days and it had 3 resources working on it, 10 hours daily. This method is more accurate then analogous estimation

Three-point estimation technique

It is used when there is a great deal of uncertainty about duration. We use these parameters and use in the formulas below.


M = most likely | O = optimistic | P = pessimistic | E = expected duration

  • Triangular Distribution:       E = (P + M+ O) / 3
  • Beta Distribution (also called PERT - Program evaluation and review technique):      E = (P + M(4) + O) / 6


Beta Distribution is preferred in cases where we have a lot of historical data.  When there is no historic data, only with guesses, use Triangle Distribution.

Using these duration estimation techniques, you can get near-to-accurate duration value. It is much better than just guessing a wrong duration, which will negatively effect the project end date

Characteristics of a Project Activity (PMI-SP)

Activities are work to be performed. The project activities have the following characteristics:

Activity owner: a single person accountable for its performance. That person also reports progress on the activity.


Activity description: Name like ‘pour wall’ is self explanatory but some detail should be added such as ‘pour the east wall from top to bottom’.


Continuity of activity: Activity should represent continuous work. If any break to be added in activity, it is better to split the activity from breakpoints. 

Activity Start and Finish dates.

Activity Duration: Ideally, activity duration should be less than two times the update cycle. For example schedule is updated after every 10 days. The activity duration should be 5 or less. 

  • This is to allow reporting of the start and finish of the activity within one or two update cycles. 
  • This helps the management to focus on performance.
  • This is not applicable on Summary, Level-of-Effort (LoE) and Hammock activities.

How Critical Path is Identified and What Information It Yields

Critical path is identified with the use of Critical Path Method (CPM), which involves identifying:

  • Activity duration

  • Activity relationships (any relationship i.e. SS, FF, FS, SF)

  • Activities with zero Total Float (activities which can’t be delayed. If delayed, project end date will be effected)

This resultant critical path gives us the following:

  • Longest path (longest set of activities) in the project. In other words it gives us project duration
    Project end date.

  • Critical Path activities (activities that fall on Critical Path which also have zero Total Float)
    Early and Late dates of activities (detail in next slide)

Free Joomla! templates by Engine Templates