Sample Schedule Management Plan (According to PMBOK)
Project Name: Project Number: |
Prepared By: Author’s Name Here |
Last Revised On: (Insert Date) |
Contents
Management Approach.
Scheduling Method.
Scheduling Tool
Schedule Processes.
Define Activities.
Sequence Activities.
Estimate Activity Resources.
Estimate Activity Durations.
Develop Schedule.
Control Schedule.
Report Schedule.
Assumptions.
Issues.
Risks.
Plan Approval
Attachments.
Management Approach
The purpose of this schedule management plan is to establish the criteria and the activities for developing, monitoring and controlling the project schedule. When this plan is approved, no schedule changes will be permitted unless a request for change is processed in accordance with the procedures set forth in the change management plan.
The project manager will assume overall responsibility for schedule management. The people listed below will assume the following schedule management responsibilities:
Roles and Responsibilities
Names / Roles |
Responsibilities |
Project Manager |
|
Project Sponsor |
|
Project Team Lead |
|
Project Team Members |
|
Project Scheduler |
|
|
|
|
|
|
|
Scheduling Method
Identify and describe the scheduling method here. The scheduling method defines the framework and algorithms used in the scheduling tool to create the schedule model.
The most common scheduling method is the critical path method (CPM). The critical path method calculates the minimum project duration and determines the amount of scheduling flexibility on the logical network paths within the schedule model.
Another scheduling method is the critical chain method. This method allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Scheduling Tool
Identify the scheduling tool here. From simple MS Excel templates to complex software applications, there are numerous scheduling tools available.
Where is the scheduling tool and who has access to it to view it? Who has access or permission to change or modify it?
Schedule Processes
Use this section and the subsections below to describe the process for developing the project schedule.
The project scheduler will initiate schedule development by adding to the schedule the deliverables found in the project work breakdown structure (WBS). The WBS can be found in the scope management plan.
Define Activities
Defining activities refers to the process of identifying and documenting the specific actions to be performed to produce the project deliverables. Examine the work breakdown structure (WBS) found in the scope management plan. Typically, deliverables represent the highest or most broadly defined part.
Work packages are the next smallest part. They exist within each deliverable.
Within each work package, there are work activities. Work activities represent the smallest level of decomposition. Place all identified work activities on the activity list.
Activity List
Identify the person or persons responsible for reviewing the project deliverables, the work packages and then defining the related work activities. Describe the process of decomposition. Will rolling way planning be used? Who will validate the defined work activities?
Milestone List
Milestones represent significant points or events in the project.
Sequence Activities
Sequencing activities is the process of identifying and documenting relationships among the project activities. Sequencing can be performed using project management software or by using manual techniques.
If the precedence diagramming method (PDM) is used to construct the schedule model, every activity and milestone except the first and the last will be connected to at least one predecessor with a finish-to-start or start-to-start logical relationship and at least one successor with a finish-to-start or finish-to-finish logical relationship. Lead and lag time may be used between activities to support a realistic project schedule.
Identify the person or persons responsible for sequencing work activities. Identify the person or persons responsible for determining dependencies and establishing leads and lags to define the relationships between project activities. Will a project schedule network diagram be developed? If so, who is responsible for developing it?
Schedule Constraints
List all schedule constraints here. Must the project be complete by a specified date? Must a deliverable be delivered before a specified date?
Activity Attributes
Activity Attributes.
Estimate Activity Resources
Estimating activity resources involves estimating the type and quantities of material, human resources, equipment or supplies required to perform each activity. Who is responsible for estimating the activity resources?
Units of Measurement
Define units of measurement for each resource. For example, are you referencing gallons or liters? How many hours in a day? How many days in a work week?
What tools and techniques will be used to estimate activity resources?
Estimate Activity Durations
Estimating activity durations is the process of estimating the number of work periods needed to complete individual activities with the estimated resources. Who is responsible for estimating the activity durations?
What tools and techniques will be used to estimate activity durations?
Activity Duration Estimates
Level of Accuracy
Specify the range used in determining the activity duration estimates.
Reserve Analysis
Does the range above include an amount for contingencies (time reserves)? Are contingency reserves added anywhere in the schedule? If so, how are they calculated, for what purpose are they provided and where are they included?
Develop Schedule
Developing the project schedule involves analyzing activity sequences, durations, resource requirements and schedule constraints to create the project schedule model. Identify the person or persons responsible for developing the project schedule.
After initial schedule development, will the schedule be reviewed and validated by the project team? Who will review the schedule with the project team and what project team members will be responsible for validating it?
Will the project sponsor be involved in preliminary schedule reviews? Will he or she participate in validating the schedule? Who will prepare the schedule model?
What will be the format of the schedule model? Gantt chart? Milestone chart? Project schedule network diagram?
Control Schedule
Controlling schedule involves monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
Schedule Baseline
The schedule baseline is included below as Attachment E. After this version of the schedule is approved, the schedule can only be changed through the formal change control procedures set forth in the change management plan. The schedule baseline will be used throughout the project as a basis for comparison to actual results.
Variance Threshold
Identify the amount of schedule variation that triggers a warning. What happens if a warning is triggered?
Identify the amount of schedule variation that triggers corrective action. What might corrective action entail?
Identify the amount of schedule variation that requires submission of a change request.
Report Schedule
The project manager will review and update the project schedule every Monday and Thursday. On these dates, members of the project team will provide the project manager with actual performance and completion information.
The project manager will compare the actual information to the schedule baseline and calculate the completion percentages and any variances. The project manager will distribute the actual schedule information according to the terms set forth in the communication management plan.
Where necessary, the project manager will meet with the project team members to determine the cause of any variance and discuss appropriate corrective measures. Where schedule changes are necessary, the project manager will submit a change request in accordance with the change management plan.
Assumptions
While planning and managing the project schedule, it’s possible that assumptions will be made. All assumptions regarding the project schedule are documented here then transferred to the Risk Management Plan for further management.
Assumption |
Date Transferred to Risk Management Plan |
|
|
|
|
|
|
|
|
Risks
While planning and managing the project schedule, risks may be identified. All risks regarding project schedule are documented here then transferred to the Risk Management Plan for further management.
Risks |
Date Transferred to Risk Management Plan |
|
|
|
|
|
|
Issues
While planning and managing schedule, it’s possible that issues will be encountered. All issues regarding the project schedule are documented here then transferred to the Risk Management Plan for further management.
Issues |
Date Transferred to Risk Management Plan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Plan Approval
By signing below, I, ______________________ in my capacity as Project Sponsor approve of this Schedule Management Plan.
Full Name:
Job Title:
___________________________________ _____________________________
Signature Date Approved
Attachments
If you are going to include activity list, milestone list, schedule baseline or anything else as an attachment, write name of the attached documents here.