By using this website, you agree to the use of cookies as described in our Privacy Policy.

Schedule Model Development Approach Explained

The schedule model development approach includes tasks such as:

Selecting data for:

  • Creating activities
  • Resources
  • Calendars
  • Work Breakdown Structure (WBS)
  • Milestones
  • Lags
  • Dependencies
  • Activity duration

This data can be gathered in team meetings, BoQs (Bill of quantity), etc.  

Further, we also choose:

  • Schedule model presentation forms e.g. Gantt Chart, table, milestones, network diagram, simple list.
  • Schedule life cycle type. Schedule Life cycles are explained here.

Various sources can be referred to for help when defining schedule development approach, explained here.

  • Hits: 1310

Characteristics of a Project Activity (PMI-SP)

Activities are work to be performed. The project activities have the following characteristics:

Activity owner: a single person accountable for its performance. That person also reports progress on the activity.


Activity description: Name like ‘pour wall’ is self explanatory but some detail should be added such as ‘pour the east wall from top to bottom’.


Continuity of activity: Activity should represent continuous work. If any break to be added in activity, it is better to split the activity from breakpoints. 

Activity Start and Finish dates.

Activity Duration: Ideally, activity duration should be less than two times the update cycle. For example schedule is updated after every 10 days. The activity duration should be 5 or less. 

  • This is to allow reporting of the start and finish of the activity within one or two update cycles. 
  • This helps the management to focus on performance.
  • This is not applicable on Summary, Level-of-Effort (LoE) and Hammock activities.
  • Hits: 1289

Role of the Project Scheduler (PMI-SP)

What is the role of a scheduler? Scheduler performs many tasks. The tasks he will do will be assigned to him by a project manager. His tasks could include:

  • Gathering schedule data (milestones, activities and their attributes e.g. dates, except risk activities)

  • Attending meetings to discuss schedule, format, reporting format.

  • Revising schedule.

  • Update plan with actual progress of activities, resources productivity rates.

  • Analysis of plan and actual progress.

  • Analyzing critical path

  • Perform resource leveling

  • Creating reports of plan, actual and forecasted schedule.

  • Creating Work Breakdown Structure (WBS)

  • Creating Organizational Breakdown Structure (OBS)

  • Creating Resource Breakdown Structure (RBS)
  • Hits: 1240

Activity Duration Estimation Techniques (PMI-SP)

Analogous estimation technique:

It is a comparison technique where we look at a similar activity performed before. If more data is available, the better the estimate will be.

Parametric estimation technique:

Parameters from previous similar activity is taken. E.g. Previous activity took 5 days and it had 3 resources working on it, 10 hours daily. This method is more accurate then analogous estimation

Three-point estimation technique

It is used when there is a great deal of uncertainty about duration. We use these parameters and use in the formulas below.


M = most likely | O = optimistic | P = pessimistic | E = expected duration

  • Triangular Distribution:       E = (P + M+ O) / 3
  • Beta Distribution (also called PERT - Program evaluation and review technique):      E = (P + M(4) + O) / 6


Beta Distribution is preferred in cases where we have a lot of historical data.  When there is no historic data, only with guesses, use Triangle Distribution.

Using these duration estimation techniques, you can get near-to-accurate duration value. It is much better than just guessing a wrong duration, which will negatively effect the project end date

  • Hits: 1311

Page 8 of 15