Viewing Project Budget Information in Primavera P6
How to view budget information in Primavera? Here are the commonly used columns in Primavera to view different budget information. The budget information will help you plan the project within the approved project budget and it will also tell how much of the budget has been approved, distributed through projects in EPS or WBS Elements in the WBS Structure.
Original Budget: Initial budget allocated (Edit in column or in Budget Log tab - the very first budget)
Current Budget: Current budget (Original budget +/- what is defined in Budget Log)
Proposed Budget: Proposed new budget after budget amendments (Edited in Budget Log Tab - define the budget as logs)
Distributed Current Budget: Budget distributed down through the EPS structure (Budget defined in Original Budget field/column, rolled up to top. Shows total rolled up value on the top level EPS/WBS Element only)
Unallocated Budget: Budget left that has not been distributed down through the EPS structure (Current Budget - Distributed Current Budget)
- Hits: 1568
Answering: What is Data Date in Primavera P6
What is Data Date in Primavera? Well, it is very easy to learn about Data Date is in Primavera P6.
Data Date is the date until which the activities have progressed. Let's say you have an activity to build a wall in 1 month and someone asks you that how much wall you have built? If you answer 50%. He will not understand whether you are on schedule or not. So the questioner again asks, 50% in how much time, and you answer that you built 50% in 1st week (say, day 7th) of the month, the questioner then will understand that you are ahead of schedule. 50% was actually expected to be completed by 15th of the month.
Lets look at a different scenario. There is another wall, to be built in 1 month. Someone asks you how much you have built it so far and you answer 50%. He further asks that you have built 50% of it in how much time and you answer that 50% is built in 3rd week of the month (say, day 21st). The questioner now understands that you are going slow because 50% had to be completed by 15th of the month.
So, the day until you have done the work is Data Date. In the above example, day 7 and day 21 were Data Dates for the activities.
Hence, after you enter progress for your activities, you must enter Data Date to specify that the progress you have entered is accomplished until what date. By entering Data Data, Primavera determines whether you are ahead or behind schedule, and reschedules the activities, to either finish on date as planned, finish earlier or later than the baseline date, depending on how much your activity has progressed until the Data Date, while comparing also the baseline.
Also learn:
- Hits: 1812
What is Scheduling Software?
What is Scheduling Software
Scheduling software helps in project schedule management. It is software that contains features, algorithms to manipulate activities with dependencies and resources to create schedule model and schedule presentations.
The scheduling software also allows to adjust various schedule parameters (e.g. duration, relationship, dates, resources, constraints, etc.) Furthermore:
- It lets you create baseline and record actual progress.
- It lets you analyze project progress against baseline and trends over periods.
- You can compare different schedule with each other.
- You can analyze resource allocation and level resources.
- You can optimize project plan to meet the end date, the budget and other constraints.
So what is scheduling software in a nutshell? It is a software application that helps you plan, execute, track and report on projects, including project activities, resources and cost. One of the most famous scheduling software being used worldwide is Primavera P6. The two most widely and commonly used scheduling software are described here.
Also read:
- Hits: 1317
Purpose of Schedule Strategy (PMI-SP)
Before planning and scheduling project activities, it is important to define:
- What will be the components of schedule
- How project schedule will be created
- How schedule will be updated
- How schedule will be analyzed
- How schedule performance will be measured
- Are there any policies, approaches, regulations to follow for project planning, scheduling, updating and configuration management.
Therefore, the above things are well planned before we move onto the scheduling planning phase.
In order to accomplish schedule strategy, various plans are created. Furthermore schedule methodology, schedule approach, presentation format, scheduling tool, schedling approval process, role of the scheduler and many more such important things are considered and finalized.