Difference Between Total Float and Free Float in Primavera P6

Both Total Float and Free Float are very important values in Primavera. The planning engineer should keep an eye on both Float types, so that decision making becomes quicker and easier if anything needs to be changed in the plan.

Let's learn what Total Float and Free Float are in Primavera.

Total Float:

By definition Total Float is "number of days an activity can be delayed without delaying project finish date".   Let's understand Total Float more with an example:

Example 1:

Activity A Finish Date: 10 March.  Project Must Finish Date (Deadline) is 20 March. Activity A can be delayed until 20 March, hence delay of 10 days. So, Total Float for Activity A is 10 days.

Example 2:

Activity B Finish Date is 15 April. Project Must Finish Date is 15 April. We can see that Activity B can not be moved forward as it is already finishing on last day of project. So, Total Float of Activity B is 0 days.

Total Float of an activity can be dependent on Total Float of another activity, if both are linked with each other. For example:

Activity A --> Activity B  (Linked with Relationship)

Total Float of Activity B is 0 days.  So, Total Float of Activity A is also 0 because if it moves forward, it will move Activity B forward, hence Activity A can't be moved.  Put another way, the activities are linked, the Total Float of an Activity is the same of the last linked activity.

Free Float:

It is number of days an activity can be delayed without delaying the successor activity.  An activity, when linked with another activity always has 0 Free Float because if it moves, it will also move its successor activity. The activity can have more than 0 Free Float also in case when it has more than one successor and lag between one of the successor activities is longer than of the other successor. 

Remember that Float is also called Slack. If you use Microsoft Project, there is no word Float in there, instead the word Slack is used.

Recommended for you:  Two types of critical activities:  longest path and total float=0 explained

  • Hits: 1519

PMP Exam Prep: 1000+ Practice Questions Free PDF Download

Are you looking for free PMP exam sample questions? Find in the link below 1000+ sample practice questions, with answers and explanation.

Download the free PMP exam questions 6th edition PDF 

Tags: free pmp exam questions 6th edition, pmp practice exam 6th edition free, pmp exam questions pdf, pmp 6th edition sample questions free

  • Hits: 1435

Sample Activity Cost Estimate Template (According to PMBOK)

ACTIVITY COST ESTIMATES

 

Project Name

 

Date

 

Project Number

 

Document Number

 

Project Manager

 

Project Owner/Client

 

 

  • Hits: 1826

Sample Activity Attributes Template (According to PMBOK)

ACTIVITY ATTRIBUTES

 

Project Name

 

Date

 

Project Number

 

Document Number

 

Project Manager

 

Project Owner/Client

 

 

  • Hits: 1421

Page 10 of 15